Bathurst Quay Neighbourhood plan (BQNP) Implementation project update


Bathurst Quay Neighbourhood plan (BQNP) Implementation Project update

Overview of key dates.


  1. New waterfront promenade – Fall 2020 completion.

  2. Transportation improvements – April 2020 construction start; Summer 2020 completion.

  3. Ireland Park Interpretive & Cultural Centre Spring 2020 Consultation; Summer 2020 construction start. Summer 2021 opening.

  4. New waterfront plaza & event space Fall 2020 consultation. 2020 Design; 2021 construction start; Phased opening 2021 and 2022.

  5. TDSB sports field enhancements Spring 2020 consultation; 2020 Design; 2021 construction; Opening 2021.

  6. Streetscape improvements Fall 2020 consultation; 2020 Design; 2021 construction; Opening 2021.

  7. Canada Malting Silos rehabilitation Part 1: 2020 Design; 2021 construction start. Part 2: EOI/RFP late 2020/early 2021.

1: New waterfront promenade construction underway. November 2019 and March 2020 (above).

3: Ireland Park Interpretive & Cultural Centre
4: New proposed waterfront plaza & event space (current state in lower photograph).
7: Canada Malting Silos rehabilitation

7. Canada Malting Silos rehabilitation: Part 1: Repair Scope of Work

Design, Tender Docs, Contract Admin & Construction Management for: – New roofing system Power supply and roof anchor system Exterior wall repairs Heritage Conservation Plan Removal of perimeter fence Water and sanitary service investigation (co-ordinated with plaza design and construction)


Part 2: Repurpose